Office Building – Stevenage LTHW Expansion Vessel

We were called to investigate a repeated history of expansion vessel diaphragm failures. An Ultrasound examination of the vessel thickness revealed thinning of the metal and a subsequent internal examination showed severe corrosion with a sharp edge puncturing the diaphragm. The thinning of the vessel represented a risk of vessel failure and the safe option was to replace the vessel.

Acorn completed a £128,000 contract for a University on Merseyside

install-case-2-1b
AquaTech Pressmain HY9 variable speed booster set

Acorn completed a £128,000 contract for a University on Merseyside. The project involved the installation of a bespoke AquaTech Pressmain HY9 variable speed booster set.

As well as supplying the HY9AV, an 8” ABS ring main (approx. 100m of pipe was installed, much of it at high level) around the Hydraulics Laboratory with various ‘take offs’ to run a selection ofexperiments where the movement of water is required. These vary from powering both Francisand Pelton turbines, to supplying water to experiments where wave patterns are used to create an ‘hydraulic jump’ to simulate the effects of a tsunami.

The work was completed over a ten week period, with commissioning taking place at the end of the project.

The Tate & Lyle Estate – East London

Acorn was called to the Tate & Lyle Estate in East London after their incumbent pump maintenance contractor failed to solve or respond to an emergency situation on a Pullen Hydropak water booster set. The water booster set had a catalogue of faults including burnt out and leaking pumps, a failed and leaking accumulator and non functioning controls.

The unit was also over sized for the application and beyond economical repair. As the estate had no water a temporary supply was connected, whilst a new Aquatech Pressmain HY3AV 10-6 booster was built and then installed just seven days from receipt of an order, normally this would take 4 or 5 weeks.