Customer approached Acorn to advise on solution of underground water course running in leisure centre main boiler plant room. Following site meeting below works were agreed:-
- Employed vacuum tanker/jetter unit to remain onsite throughout duration of works to empty pump chamber & keep level down to minimum whilst works are being carried out.
- Confined space man entry into well to clean out main side of pump chamber.
- Removed 5 bucket loads of silt/debris.
- Drilled pump stools to base of chamber.
- Cut out & removed existing pumps & pipework/non-return valves.
- Installed new pipework & non-return valve.
- Connected to existing external pipework.
- Measured & cut guiderails, secured.
- Installed 2no. new submersible pumps.
- Supplied & installed 4no. new float switches & set levels accordingly.
- Installed & connected new upgraded control panel.
- Setup & commissioned unit into system.
- Alleviating flood issues & protecting new boiler installation.